Emerson to Install Gas Turbine Controls Within Aggressive Timeframe at ENGIE Combined-cycle Power Plant in France

Dunkirk

ENGIE has awarded Emerson a contract to retrofit controls on Alstom GT13 combustion turbines at its DK6 combined-cycle power plant in Dunkirk, France. High resolution image







Retrofitting controls on Alstom GT13 combustion turbines with Ovation™ technology expected to boost reliability and provide flexibility to support future expansion at DK6 plant

PITTSBURGH (November 6, 2017) — ENGIE has awarded Emerson a contract to replace legacy combustion turbine controls with Ovation™ turbine control technology at its DK6 800-MW combined-cycle power plant in Dunkirk, France. 

The Ovation controls will be installed at each unit during a 13-day outage – a compressed timeframe for a turbine controls replacement project. This marks the first time a vendor other than the turbine OEM has been selected to retrofit GT13 combustion turbine controls.

“We considered different suppliers, and ultimately chose Emerson because its Ovation system met our requirements for support and maintenance over the expected 20-year life of the plant,” said DK6 Plant Manager Bernard Rulmont.

Flexibility was another factor in ENGIE’s decision to select Emerson, according to Rulmont.
Ovation is an open system, which gives DK6 personnel the ability to modify applications or adapt the controls to accommodate future plant expansion, as well as new operation modes and fuels – all without the need for a costly service call.

“Emerson understands the impact efficient turbine control has on achieving optimal levels of reliability and availability,” said Bob Yeager, president, Power & Water, Emerson Automation Solutions. “Our Ovation technology uses the same hardware and software platform for turbine control as it uses for other plant controls, such as heat recovery steam generators, burner management systems, generator excitation and high-fidelity embedded simulation. This single platform architecture significantly reduces O&M automation-related expenses and simplifies lifecycle management and planning.”

The first retrofitted power block is expected to be back online in September 2018; the second in July 2019. Emerson’s comprehensive project scope includes dismantling the existing controls, engineering and installing the new controls, and assisting with commissioning and startup.

미디어:
• 연락처: 에머슨 글로벌 미디어 연락처

추가적인 정보:
에머슨 Exchange 365 커뮤니티
X Facebook LinkedIn YouTube 를 통해 에머슨과 연결되어 보세요.

에머슨에 대해 
에머슨(NYSE: EMR)은 전 세계의 중요한 산업에 혁신적인 솔루션을 제공하는 글로벌 테크놀러지 소프트웨어 회사입니다. 에머슨은 AspenTech의 대주주로, 선도적인 자동화 포트폴리오를 통해 하이브리드, 공정, 개별 제조업체가 운영 최적화, 인력 보호, 탄소 배출 저감, 지속 가능성 목표를 달성할 수 있도록 지원하고 있습니다. 자세한 내용은 Emerson.com을 방문하십시오.

이 웹 사이트를 사용하려면 JavaScript를 활성화하세요.